G
Gizzmo
I need help developing and understanding how to distribute project cost
over time (i.e. by month). I would also like to change the distributio
and skew of the costs. For example say the costs are spread over
months based on a normal distribution curve, I would like to:
one: change the number of months say from 8 to 12, using start and en
dates/periods
two: change the skewness (I think this is the right terminology!) s
that the project costs are 'front' loaded (i.e. skewed to the left) o
'back' loaded (i.e. skewed to the right).
Any assistance would be appreciated
I have attahced a file of what I have done so far:
Table 1: represents % spread of project cost over 1 to 60 periods (i.e
months) using a normal distribution NOTE due to file upload size I hav
deleted this section
Table 2: represents $ spread of project cost over 1 to 60 periods (i.e
months) using a normal distribution NOTE due to file upload size I hav
deleted this section
Table 3; is my attempt to 'skew' the spread of project costs by changin
column A and B values and display them as barred/bell curve. NOTE I hav
deleted the bell curve due to file upload size.
Hope I have provided enough for someone to help.
Thank
+-------------------------------------------------------------------
|Filename: Spread Project Costs (2).zip
|Download: http://www.excelbanter.com/attachment.php?attachmentid=770
+-------------------------------------------------------------------
over time (i.e. by month). I would also like to change the distributio
and skew of the costs. For example say the costs are spread over
months based on a normal distribution curve, I would like to:
one: change the number of months say from 8 to 12, using start and en
dates/periods
two: change the skewness (I think this is the right terminology!) s
that the project costs are 'front' loaded (i.e. skewed to the left) o
'back' loaded (i.e. skewed to the right).
Any assistance would be appreciated
I have attahced a file of what I have done so far:
Table 1: represents % spread of project cost over 1 to 60 periods (i.e
months) using a normal distribution NOTE due to file upload size I hav
deleted this section
Table 2: represents $ spread of project cost over 1 to 60 periods (i.e
months) using a normal distribution NOTE due to file upload size I hav
deleted this section
Table 3; is my attempt to 'skew' the spread of project costs by changin
column A and B values and display them as barred/bell curve. NOTE I hav
deleted the bell curve due to file upload size.
Hope I have provided enough for someone to help.
Thank
+-------------------------------------------------------------------
|Filename: Spread Project Costs (2).zip
|Download: http://www.excelbanter.com/attachment.php?attachmentid=770
+-------------------------------------------------------------------