T
-Thomas
Hi everyone!
As the topic informs, I am desperately in the need of a query that gives me
the actual hours worked by every resource for a certain period of time. I am
perticularly interested in the summary task levels, because that is our
reporting level. We have a structure like follows:
Billable work(summary task)
Product1(task)
Product2(task)
Product3(task)
So our users report their hours to a certain product, but I want to get the
actual hours reported for the summary task(Billable work). I have tried many
queries obtained from this forum by altering them but haven't succeeded yet.
So basicly I want to get the same data from the query as I can get from PWA
in the "View resource assignments" section.
I am using project server 2003.
Any help would be greatly appreciated!
As the topic informs, I am desperately in the need of a query that gives me
the actual hours worked by every resource for a certain period of time. I am
perticularly interested in the summary task levels, because that is our
reporting level. We have a structure like follows:
Billable work(summary task)
Product1(task)
Product2(task)
Product3(task)
So our users report their hours to a certain product, but I want to get the
actual hours reported for the summary task(Billable work). I have tried many
queries obtained from this forum by altering them but haven't succeeded yet.
So basicly I want to get the same data from the query as I can get from PWA
in the "View resource assignments" section.
I am using project server 2003.
Any help would be greatly appreciated!