Hello Hernandezz,
Run the following query, you will get total work by project. This
query will give all the column values that you see in PWA Project
Center.
***********************************************************************************************
SELECT MSP_EpmProject.ProjectName AS ProjectName,
MSP_EpmTask.TaskStartDate AS Start,
MSP_EpmTask.TaskFinishDate AS Finish,
MSP_EpmTask.TaskPercentCompleted AS '%Complete',
MSP_EpmTask.TaskWork AS WorkinHrs,
MSP_EpmTask.TaskActualWork AS ActualWorkinHrs,
MSP_EpmTask.TaskDuration/8 AS DurationDays,
MSP_EpmTask.TaskPercentWorkCompleted AS '%WorkComplete',
MSP_EpmResource.ResourceName AS Owner
FROM MSP_EpmTask INNER JOIN
MSP_EpmProject ON MSP_EpmTask.ProjectUID = MSP_EpmProject.ProjectUID
INNER JOIN
MSP_EpmResource ON MSP_EpmProject.ProjectOwnerResourceUID =
MSP_EpmResource.ResourceUID
WHERE (MSP_EpmTask.TaskOutlineLevel = 0) AND
(MSP_EpmTask.TaskOutlineNumber = 0)
*******************************************************************************************************************
Thanks
Chakhttp://
www.epmcentral.com- Hide quoted text -
- Show quoted text -