Links always model the earliest time a task CAN start, not necessarily when
they WILL start. If A->C and B->C, both links SS, both A & B will need to
start before C can start since the first link says the earliest C can start
is when A is underway and and the second link says the earliest C can start
is when B has started. Can't really think of a way to model an either/or
relationship with C starting on the earlier of the two events
--
Steve House [MVP]
MS Project Trainer/Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Dave Francis said:
Is it possible for 2 tasks (A and B) to be link to a third (C) in such a
way that C will start as soon as either A or B are started?
You can use a SS relationship for one task, but what do you use for 2 or
more tasks.