Staffing gaps between activities

D

David Telford

We have a large fixed-bid project we're staffing. Because it's fixed bid, we need to account for hours spent between activities. So if I'm on Activity1 from M - Th in Week 1 and Activity 2 runs W - F in Week 3, we need to account for F in Week 1, all of Week 2, and M - T in Week 3 as I will be on the project for numerous miscellaneous tasks. What's the best way to set this up in the project plan so that my time appears to be dedicated to the project for the entire duration, yet I'm still listed as a working resource on various activities, all without overloading my resource for the days when I'm working an activity/task? Thanks.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top