D
David Telford
We have a large fixed-bid project we're staffing. Because it's fixed bid, we need to account for hours spent between activities. So if I'm on Activity1 from M - Th in Week 1 and Activity 2 runs W - F in Week 3, we need to account for F in Week 1, all of Week 2, and M - T in Week 3 as I will be on the project for numerous miscellaneous tasks. What's the best way to set this up in the project plan so that my time appears to be dedicated to the project for the entire duration, yet I'm still listed as a working resource on various activities, all without overloading my resource for the days when I'm working an activity/task? Thanks.