Standard Base Calendar

S

Steve

Hi,

The standard base calendar has national holidays (as well as weekends) as
non-working time. Someone set it up this way I guess, but how? I'd like to
reset the standard calendar to weekends only non-working time but "set
selected date(s) to" is denied so I cannot reset the holidays to "use
default". I have administrator privileges (apparently). What can I do
please?

Plus, although I use a new base calendar for a project calendar (without the
holidays) so a task of 5 days lasts a week, the non-working time holiday in
the standard base calendar shows up on the Gantt so I see four days. I'm
puzzled.

Thank you.
 
D

Dale Howard [MVP]

Steve --

Is this a Project Server question? If so, you need to indicate this in your
message. Assuming you are using Project Server and you are a Project Server
administrator, you either need to open the Enterprise Global first (Project
Server 2003) or navigate to the Server Settings page in PWA and click the
Enterprise Calendars link in the Enterprise Data section of the page. Also,
if this is a Project Server question, please post your future questions
about Project Server in the microsoft.public.project.server newsgroup, as
this newsgroup is dedicated to the Microsoft Project desktop application
only. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top