S
Steve
Hi,
The standard base calendar has national holidays (as well as weekends) as
non-working time. Someone set it up this way I guess, but how? I'd like to
reset the standard calendar to weekends only non-working time but "set
selected date(s) to" is denied so I cannot reset the holidays to "use
default". I have administrator privileges (apparently). What can I do
please?
Plus, although I use a new base calendar for a project calendar (without the
holidays) so a task of 5 days lasts a week, the non-working time holiday in
the standard base calendar shows up on the Gantt so I see four days. I'm
puzzled.
Thank you.
The standard base calendar has national holidays (as well as weekends) as
non-working time. Someone set it up this way I guess, but how? I'd like to
reset the standard calendar to weekends only non-working time but "set
selected date(s) to" is denied so I cannot reset the holidays to "use
default". I have administrator privileges (apparently). What can I do
please?
Plus, although I use a new base calendar for a project calendar (without the
holidays) so a task of 5 days lasts a week, the non-working time holiday in
the standard base calendar shows up on the Gantt so I see four days. I'm
puzzled.
Thank you.