By opening the Enterprise Global, we can use the "Change Working Time.."
feature under the "Tools" menu to mention any non-working days for the year.
But some of the resources for any critical projects within the organization
might have to be working on such days as well. What could be the possible
solution for such case? Is is possible to define calendars for each
project/group of projects? So that we can somehow allow the PMs to define
their own calendars/non-working days?
Looking forward.
Regards,
Haris
By opening the Enterprise Global, we can use the "Change Working Time.."
feature under the "Tools" menu to mention any non-working days for the year.
But some of the resources for any critical projects within the organization
might have to be working on such days as well. What could be the possible
solution for such case? Is is possible to define calendars for each
project/group of projects? So that we can somehow allow the PMs to define
their own calendars/non-working days?
Looking forward.
Regards,
Haris