L
Leonid
We are using Project Professional 2007 + Project Server 2007 in our company,
but now we've met too complicated way of our resource management. In order to
simplify it, I would like to better understand how environment of Project
Server 2007 considers the project planning cycle. Please consider own
business case and confirm whether proposed implementation of resource
management feature is ok.
=========
Business case description
Our project management is based on our own methodology (basing on PMBOK).
The standart lifecycle of projects is Initiation -> Planning -> Executing ->
Closing.
We have 1 resource pool (~20-30 people) which we want to plan. We consider
following 3 roles:
- Project Manager
Responsible for management of scope (define WBS), developing the basis for
the schedule (define links between tasks and determine duration of tasks)
- Resource Manager
Responsible for leveling resources and resource utilization
- Team member
Make work assigned
========================
Technical solution
We consider implementing following decision according to life-cycle of
project:
1. Project is authorized
======== Planning ======
2. Project Manager (PM) defines the basis of the project, including
preliminary scope, and role-based resources
3. PM creates the MS Project plan. PM puts the task “Develop the schedule of
project XXX / Phase YYY (if applicable)†to the schedule of the project and
save the project. PM uses role-based generic resources which must be already
included in Resource Pool by Resource Manager (RM)
4. RM checks the plan, change generic resources to specific, and level the
project if necessary. RM publishes the plan. This way RM approves the request
of PM for resources.
5. PM with team assigned develop the project scope (WBS), evaluate the work
necessary for each assignment, develop links between tasks. After this PM
saves this preliminary plan in MS Project.
6. RM checks the plan, if some generic resources are still used changes them
to specific, levels the resources taking into account other projects, and
publishes the plan.
====== Executing (and Monitoring) ======
7. Works are done according to the schedule published.
8. Each week (or other basis for tracking) RM republishes all projects which
includes work done this week.
9. If some changes in the schedule are necessary, we need to return on
planning (step 5 and 6)
====== Closing ======
10. PM uses the custom enterprise field "Open / In archive" to mark the
project as archived.
11. RM checks that all assignment are completed and republish project.
but now we've met too complicated way of our resource management. In order to
simplify it, I would like to better understand how environment of Project
Server 2007 considers the project planning cycle. Please consider own
business case and confirm whether proposed implementation of resource
management feature is ok.
=========
Business case description
Our project management is based on our own methodology (basing on PMBOK).
The standart lifecycle of projects is Initiation -> Planning -> Executing ->
Closing.
We have 1 resource pool (~20-30 people) which we want to plan. We consider
following 3 roles:
- Project Manager
Responsible for management of scope (define WBS), developing the basis for
the schedule (define links between tasks and determine duration of tasks)
- Resource Manager
Responsible for leveling resources and resource utilization
- Team member
Make work assigned
========================
Technical solution
We consider implementing following decision according to life-cycle of
project:
1. Project is authorized
======== Planning ======
2. Project Manager (PM) defines the basis of the project, including
preliminary scope, and role-based resources
3. PM creates the MS Project plan. PM puts the task “Develop the schedule of
project XXX / Phase YYY (if applicable)†to the schedule of the project and
save the project. PM uses role-based generic resources which must be already
included in Resource Pool by Resource Manager (RM)
4. RM checks the plan, change generic resources to specific, and level the
project if necessary. RM publishes the plan. This way RM approves the request
of PM for resources.
5. PM with team assigned develop the project scope (WBS), evaluate the work
necessary for each assignment, develop links between tasks. After this PM
saves this preliminary plan in MS Project.
6. RM checks the plan, if some generic resources are still used changes them
to specific, levels the resources taking into account other projects, and
publishes the plan.
====== Executing (and Monitoring) ======
7. Works are done according to the schedule published.
8. Each week (or other basis for tracking) RM republishes all projects which
includes work done this week.
9. If some changes in the schedule are necessary, we need to return on
planning (step 5 and 6)
====== Closing ======
10. PM uses the custom enterprise field "Open / In archive" to mark the
project as archived.
11. RM checks that all assignment are completed and republish project.