G
Gary Furash
I wanted to toss this out and see what the "best
practice" was for the following:
1. Milestone Placement
For a milestone representing the completion of a task and
its subtasks, do you typically place it indented under
the parent task as the last task, linking it to all of
the child tasks, or after, linked to the task. The
latter is easier but I've seen it done both ways.
2. Task v subtask linking
When essentially linking two subtasks from different
tasks, do you link the successor to the predecessor
subtask or the predecesor's parent task. The latter is
easier, but the former is probably more accurate.
practice" was for the following:
1. Milestone Placement
For a milestone representing the completion of a task and
its subtasks, do you typically place it indented under
the parent task as the last task, linking it to all of
the child tasks, or after, linked to the task. The
latter is easier but I've seen it done both ways.
2. Task v subtask linking
When essentially linking two subtasks from different
tasks, do you link the successor to the predecessor
subtask or the predecesor's parent task. The latter is
easier, but the former is probably more accurate.