S
Sneha Satish
Hi All,
My organization has implemented EPM 2003 successfully. For a particular
project each role has a particular cost rate attached. Now these costs have
changed.
For Example SE - Current cost say is $10 and the new cost is say $15.
I would like to know if we could change the Standard rate for the resource
without affecting the current project since the new cost would be applicable
to the new projects.
My organization has implemented EPM 2003 successfully. For a particular
project each role has a particular cost rate attached. Now these costs have
changed.
For Example SE - Current cost say is $10 and the new cost is say $15.
I would like to know if we could change the Standard rate for the resource
without affecting the current project since the new cost would be applicable
to the new projects.