P
Pr4gm4tik
It was suggested that I post this to the Project Server group after I posted
it in the general forum, but please know that I am actually trying to set the
start and end dates using Project Professional 2007, not on Project Server
using PSI.
I am inserting tasks into the project from another system using a .net
utility running against the Project Pro 2007 object model.
I need to set absolute start and end dates for tasks -- I do not want
Project Pro to change these dates for any reason. I have turned off
automatic calculation for the project, but it still seems to adjust the dates
as it seems fit.
The reason this is important is the project is being published to Proj
Server 2007, and tasks can only be auto-populated in the user's timesheet if
the task is scheduled within the timesheet period, so I need to make the date
range wide enough to cover all possible timesheet periods.
it in the general forum, but please know that I am actually trying to set the
start and end dates using Project Professional 2007, not on Project Server
using PSI.
I am inserting tasks into the project from another system using a .net
utility running against the Project Pro 2007 object model.
I need to set absolute start and end dates for tasks -- I do not want
Project Pro to change these dates for any reason. I have turned off
automatic calculation for the project, but it still seems to adjust the dates
as it seems fit.
The reason this is important is the project is being published to Proj
Server 2007, and tasks can only be auto-populated in the user's timesheet if
the task is scheduled within the timesheet period, so I need to make the date
range wide enough to cover all possible timesheet periods.