J
JodyJ
I have a task in a plan that is fixed duration and has a start date of
7/22/05 and a finish date of 12/22/05. There are several resources assigned
to the task.
When I "republish assignments" the start and finish dates displayed in this
window are not the same start and finish dates listed in the project plan.
They ARE the ones that get sent in the notification to resources, resulting
in much confusion.
The start and finish dates listed in the republish assignments window seem
to have something to do with when a resources has or hasn't logged time to
the task but I can't seem to discern a pattern.
Does anyone have any idea what the logic might be for these dates?
7/22/05 and a finish date of 12/22/05. There are several resources assigned
to the task.
When I "republish assignments" the start and finish dates displayed in this
window are not the same start and finish dates listed in the project plan.
They ARE the ones that get sent in the notification to resources, resulting
in much confusion.
The start and finish dates listed in the republish assignments window seem
to have something to do with when a resources has or hasn't logged time to
the task but I can't seem to discern a pattern.
Does anyone have any idea what the logic might be for these dates?