R
Robert H
I have a project with Summary tasks and tasks and at this point no
resources assigned. We are estimating tasks duration and entering them
on sub tasks. We trying to look at overall duration. I’ve noticed
that the Duration Field (column) calculates duration as duration of
worked days and does not simple look at Finish – Start for an
“overall” duration. I set up a custom duration field “Total Duration”
with the formula ProjDateDiff([Start],[Finish]) which I proofed by
comparing with Finish – Start date calculations in Excel. However,
some summary tasks show zero days in the custom Total Duration field
even though there are days (many) in the respective start and finish
fields.
I’m lost as to why this is happening. Hopefully someone can point me
in the right direction.
Robert
resources assigned. We are estimating tasks duration and entering them
on sub tasks. We trying to look at overall duration. I’ve noticed
that the Duration Field (column) calculates duration as duration of
worked days and does not simple look at Finish – Start for an
“overall” duration. I set up a custom duration field “Total Duration”
with the formula ProjDateDiff([Start],[Finish]) which I proofed by
comparing with Finish – Start date calculations in Excel. However,
some summary tasks show zero days in the custom Total Duration field
even though there are days (many) in the respective start and finish
fields.
I’m lost as to why this is happening. Hopefully someone can point me
in the right direction.
Robert