I have a task with multiple resources.
The task start date is schedule for 5/11/2009
I have a split view with "Resource Schedule" on bottom
One resource has enter actual hours on 5/12/2009.
All the other resource show a start date of 6/19/2009.
Here is what I do:
I change one of the resources start date to 5/11/2009.
All the others are reset to 5/11/2009 except for the resource with actual
hours.
OK... so far
Then I try pushing one of the other resources back to 6/19/2009 and click OK.
The date is 6/19/2009 and a second later is reset to 5/11/2009.
Why is the date for that resource reverting back to 5/11/2009?
The task start date is schedule for 5/11/2009
I have a split view with "Resource Schedule" on bottom
One resource has enter actual hours on 5/12/2009.
All the other resource show a start date of 6/19/2009.
Here is what I do:
I change one of the resources start date to 5/11/2009.
All the others are reset to 5/11/2009 except for the resource with actual
hours.
OK... so far
Then I try pushing one of the other resources back to 6/19/2009 and click OK.
The date is 6/19/2009 and a second later is reset to 5/11/2009.
Why is the date for that resource reverting back to 5/11/2009?