C
crispy_noodle
Hey,
I am trying to produce my first Gannt chart using MS Project.
I have identified all the tasks that need to be completed and have split
these into summary and subtasks.
However.. i CANNOT (no matter how hard i try!) change the start date of a
summary task - it seems to be set to the project start date and I cannot
change it.
I have tried double clicking on the tasks in question, but the start and
finish dates seem to be set as default - they are in light grey and I cannot
change them.
Any help would be greatly appreciated, I'm getting so frustrated!!
Many thanks x
I have tried selected the task,
I am trying to produce my first Gannt chart using MS Project.
I have identified all the tasks that need to be completed and have split
these into summary and subtasks.
However.. i CANNOT (no matter how hard i try!) change the start date of a
summary task - it seems to be set to the project start date and I cannot
change it.
I have tried double clicking on the tasks in question, but the start and
finish dates seem to be set as default - they are in light grey and I cannot
change them.
Any help would be greatly appreciated, I'm getting so frustrated!!
Many thanks x
I have tried selected the task,