Sherry
Hi,
I'm using Project 2002 with XP Pro. I'm using the Work column to ented the
required effort for each task. I have the work day defined as 8 hours. I
entered a task that must start on a Monday and entered 8 hours Work time.
The next task cannot start until the first one is finished so I established
the predecessor. Project is showing the second task as starting on Monday
instead of Tuesday as it should. This works fine when I use duration to
schedule tasks. Is there something I'm missing when using Work?
Thanks!
Sherry
I'm using Project 2002 with XP Pro. I'm using the Work column to ented the
required effort for each task. I have the work day defined as 8 hours. I
entered a task that must start on a Monday and entered 8 hours Work time.
The next task cannot start until the first one is finished so I established
the predecessor. Project is showing the second task as starting on Monday
instead of Tuesday as it should. This works fine when I use duration to
schedule tasks. Is there something I'm missing when using Work?
Thanks!
Sherry