T
Top Spin
I am just learning Project. The Tutorial makes a big point of whether
I set up a new project with a Start Date or a Finish Date. I got the
impression that start date is the way to go for most projects, but I
couldn't find where it explained why. It did talk about losing various
settings if you change from one to the other such as "leveling delays"
and "leveling splits". I don't know what those are and if I even need
them.
I have a software project that I am doing more or less in my spare
time, but I have a couple of contract programmers and some other
external dependencies. I'd like a way to keep track of all of the
little tasks and interdependencies.
I don't really have a "deadline", per se. I would like to enter the
various tasks and time estimates for each and then let the
interdependencies tell me when it will be done. Is that a reasonable
way to go?
That seems to me to suggest that I not use a Finish Date. Is that
right? I just don't want to enter a lot of data and run into
conversion problems later.
Thanks
I set up a new project with a Start Date or a Finish Date. I got the
impression that start date is the way to go for most projects, but I
couldn't find where it explained why. It did talk about losing various
settings if you change from one to the other such as "leveling delays"
and "leveling splits". I don't know what those are and if I even need
them.
I have a software project that I am doing more or less in my spare
time, but I have a couple of contract programmers and some other
external dependencies. I'd like a way to keep track of all of the
little tasks and interdependencies.
I don't really have a "deadline", per se. I would like to enter the
various tasks and time estimates for each and then let the
interdependencies tell me when it will be done. Is that a reasonable
way to go?
That seems to me to suggest that I not use a Finish Date. Is that
right? I just don't want to enter a lot of data and run into
conversion problems later.
Thanks