A
Ally
I've set tasks to have predecessors and given everything a 'start ASAP'
constraint. I've been entering hours worked (and having allocated days and
actual duration visible, as well as a set baseline) and then, when the task
is complete, changing the allocated days to match the actual duration so we
can see how quickly the tasks are progressing.
What I would like to do is have the start and finish dates automatically
update according to the hours/days the predecessing task took.
Help?
constraint. I've been entering hours worked (and having allocated days and
actual duration visible, as well as a set baseline) and then, when the task
is complete, changing the allocated days to match the actual duration so we
can see how quickly the tasks are progressing.
What I would like to do is have the start and finish dates automatically
update according to the hours/days the predecessing task took.
Help?