J
Jim Jones
Some help needed for a Project novice.
I am using Project to plan the the administration of a nationakl school
examination. At the moment, my plan is not much more than a 'to do list'
containing about 250 tasks. However, I have ambitions to use Project in a
much more productive way.
At the moment, I am stuck with a problem. I am experiencing problems with
some of my start dates which seem to change for no reason. For example, this
moring, although my plan starts on 01/01/08, about 6 dates had changed to
dates in 2005 and 2006 (and they were all Saturdays!). I have been sorting
using Resource Names and Start Dates, and I have the "permanently renumber
tasks" box ticked, but otherwise I have been nothing more than adding tasks
and writing in the Notes field.
Any help would be much appreciated.
Jim Jones
I am using Project to plan the the administration of a nationakl school
examination. At the moment, my plan is not much more than a 'to do list'
containing about 250 tasks. However, I have ambitions to use Project in a
much more productive way.
At the moment, I am stuck with a problem. I am experiencing problems with
some of my start dates which seem to change for no reason. For example, this
moring, although my plan starts on 01/01/08, about 6 dates had changed to
dates in 2005 and 2006 (and they were all Saturdays!). I have been sorting
using Resource Names and Start Dates, and I have the "permanently renumber
tasks" box ticked, but otherwise I have been nothing more than adding tasks
and writing in the Notes field.
Any help would be much appreciated.
Jim Jones