J
Jodie Smith
OK, I know this has been asked a bunch of times but I am stumped. I just got project 2010 at work and for some reason none of the tasks are changingbased on the predecessors unless I delete the start and end date and the predecessor info and then retype the predecessor. Then it works. Here's whatI've checked so far:
-my tasks have a 0% complete
-I have not entered start or end date manually on any of them
-they are start as soon as possible
-I went into file options schedule and calculate project after each edit is on
So as an example, I have task A (create project plan) and task B (signoff project plan) is FS+1day
I change the duration of task A from 5 to 10days because it is taking longer than expected.
To me task B start should move but it stays the same (it used to change when I had project 2007).
This problem is through the whole project so tasks all the way along look like they are starting before they really should.
Help!
-my tasks have a 0% complete
-I have not entered start or end date manually on any of them
-they are start as soon as possible
-I went into file options schedule and calculate project after each edit is on
So as an example, I have task A (create project plan) and task B (signoff project plan) is FS+1day
I change the duration of task A from 5 to 10days because it is taking longer than expected.
To me task B start should move but it stays the same (it used to change when I had project 2007).
This problem is through the whole project so tasks all the way along look like they are starting before they really should.
Help!