A
AngePaton
I have a large project that I need to create a pivot table and various
reports on. Th e pivot table needs to display by week, the amount of hours
that are required by each resource. However, I can only export Start & Finsih
dates to Excel, I am unable to work out how to create a pivot table that will
show that a resource is working on a task over 3 months so Wk1 = 16 hrs
effort, wk2 etc..... Using grouping on the pivot doesn't work as it only
shows the week the task starts in.
Does Project have a 'work effort by week' report? The 'resource usage'
report gives me what I want, but I can't export it to Excel, is there a
way????
reports on. Th e pivot table needs to display by week, the amount of hours
that are required by each resource. However, I can only export Start & Finsih
dates to Excel, I am unable to work out how to create a pivot table that will
show that a resource is working on a task over 3 months so Wk1 = 16 hrs
effort, wk2 etc..... Using grouping on the pivot doesn't work as it only
shows the week the task starts in.
Does Project have a 'work effort by week' report? The 'resource usage'
report gives me what I want, but I can't export it to Excel, is there a
way????