Start/Finish Dates

V

Vicky

We schedule our tasks by duration of half days up to 5 days. When we have a
1-day task, how can we set start and finish times to happen on the same day?
Our working times are set up as 8am to 5pm, M-F, but the tasks shows duration
of 1.13 days with a start time of 8am and finish time of 5:02pm.

We want it to show 1 day with start at 8am and finish at 5pm. Please help us!
 