Sebastian,
Check these two formulas
IIf([% Complete]=100, "Complete
Project",IIf([Finish]>ProjDateAdd([Baseline
Finish],(ProjDateDiff([Baseline Start],[Baseline Finish],[Project
Calendar])*0.25),[Project Calendar]),"At least 25% over baseline
schedule",IIf(([Finish]>ProjDateAdd([Baseline
Finish],(ProjDateDiff([Baseline Start],[Baseline Finish],[Project
Calendar])*0.1),[Project Calendar])) And [Finish]<ProjDateAdd([Baseline
Finish],(ProjDateDiff([Baseline Start],[Baseline Finish],[Project
Calendar])*0.25),[Project Calendar]),"At least 10% over baseline
schedule","On or under baseline schedule")))
IIf([% Complete]=100,"Complete Project",IIf(IsDate([Baseline
Finish]+0)=0,"No Baseline",IIf([Finish]>ProjDateAdd([Baseline
Finish],(ProjDateDiff([Baseline Start],[Baseline Finish],[Project
Calendar])*0.25),[Project Calendar]),"At least 25% over baseline
schedule",IIf(([Finish]>ProjDateAdd([Baseline
Finish],(ProjDateDiff([Baseline Start],[Baseline Finish],[Project
Calendar])*0.1),[Project Calendar])) And [Finish]<ProjDateAdd([Baseline
Finish],(ProjDateDiff([Baseline Start],[Baseline Finish],[Project
Calendar])*0.25),[Project Calendar]),"At least 10% over baseline
schedule","On or under baseline schedule"))))HTH
You have to change [Project Calendar] for the calendar of your choice
Hope this helps,
Mauricio
Sebastian Cordoba said:
Hi everyone.
I need to implement a indicator which shows if a task started on time and
finished on time (comparing against Baseline values). I was thinking of
this
formula:
ProjDateDiff([Baseline Start],[Actual Start])
Is it OK? What should I change?
Thanks for your help.