Start Task two days after

M

Maanu

Hi,

I would like to start a task two days after starting another task.

Is that possibloe?

Thanks!
 
J

Jan De Messemaeker

Hi,

You can make a task start AT LEAST 2 days after an other task
Double-Click on the successor tasks's row (any cell will do) and in the
predecessor's column, select the predecessor's name or ID, type= Start to
Start, Lag=2d.
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
J

John

Maanu said:
Hi,

I would like to start a task two days after starting another task.

Is that possibloe?

Thanks!

Maau,
Yes, the simplest structure is with a lag in the task's predecessor. For
example, if you want task 11 to start 2 working days after task 10, the
the Predecessor for task 11 should be:
10SS+2d

If you want calendar days instead of working days, then use:
10SS+2ed

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top