Hello Cadilly,

No sorry. The field is either populated with a date or it shows
N/A. Without knowing why you are using the field it's difficult to
make further recommendations, but you might find creating a formula
in one of the text fields using an IIf function to test whether
Start1 = NA -- show nothing, if not NA, show Start1.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 