B
Bobg
Hello,
I am new to using baselines, but would like to begin using them. I have a
saved copy of my project plan from about a month ago that I would like to use
as my baseline dates. Since then there have been several changes made to the
plan (some tasks added, etc.). What is the easiest way for me to get the
information from the month old plan to be my baseline in the current version?
Should I just save a baseline in the current version and go through task by
task adjusting the baseline dates to match what they were in the older
version? What information, other than the dates, would I need to enter?
Thanks!
I am new to using baselines, but would like to begin using them. I have a
saved copy of my project plan from about a month ago that I would like to use
as my baseline dates. Since then there have been several changes made to the
plan (some tasks added, etc.). What is the easiest way for me to get the
information from the month old plan to be my baseline in the current version?
Should I just save a baseline in the current version and go through task by
task adjusting the baseline dates to match what they were in the older
version? What information, other than the dates, would I need to enter?
Thanks!