Status and % complete of predecessor task

Joined
Aug 25, 2018
Messages
1
Reaction score
0
Hi, I have a project with several tasks. Some tasks are late because theirs predecessors are late, so the tasks can't start. I need to create 2 fields that show the status and % complete of the predecessor task. For example, the task 54 depends ou task 53. I want 2 fields in line 54 showing the status and % complete of task 53. I think I can't do it using formulas. How can I do it using VBA?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top