Status date field - does it exist?

A

Alfatcop

Hello All,

Is there a field that keeps the date of the last update performed on a task?
I specifically need to track WHEN team members are:
modifying the % complete from 0% to x%
modifying the % complete from x% to 100%

I am looking for a sort of status date field.

Thank you,
 
J

Jonathan Sofer [MVP]

That would probably have to be done with a macro that copies the current
timestamp into a custom date field each time a task is touched. But could
slow down performance dramatically.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top