L
lbethel
The Status Field must be inaccurate in some cases. I see the following: If an
activity has 2 tasks under it; One of the tasks was completed in the past,
the other is scheduled in the future. The activity will always have a Late
staus. I also see that if a task has 2 resources assigned, with one's work
completed in the past, and the other planned in the future then the task will
always have a Late Status. Does anyone have incite on this? Thanks
activity has 2 tasks under it; One of the tasks was completed in the past,
the other is scheduled in the future. The activity will always have a Late
staus. I also see that if a task has 2 resources assigned, with one's work
completed in the past, and the other planned in the future then the task will
always have a Late Status. Does anyone have incite on this? Thanks