Okay, this is wierd. In MS Project, using Task Usage, I enter hours on a task
for a resource. The hours I input match the scheduled hours. I save the file,
then I publish it using 'New and Changed Assignments'. The task now shows 80%
complete. When I go to Web Access and look at the project, the progress that
I just put in Project (by entering the actual hours) shows just like in
Project. However, when I go to resource assignments in PWA and and pull up
the resource that is assigned to the task (there's only one), that task only
shows 0% and no actual hours. What's up? Do you have to input this
information into PWA for it to show in PWA?
for a resource. The hours I input match the scheduled hours. I save the file,
then I publish it using 'New and Changed Assignments'. The task now shows 80%
complete. When I go to Web Access and look at the project, the progress that
I just put in Project (by entering the actual hours) shows just like in
Project. However, when I go to resource assignments in PWA and and pull up
the resource that is assigned to the task (there's only one), that task only
shows 0% and no actual hours. What's up? Do you have to input this
information into PWA for it to show in PWA?