Hello Chris, Hello John,
I think that the Status field and the Status indicator field are not custom
fields: they are calculated by MS Project. So we don't have direct access to
there formulae.
Gérard Ducouret
PS : In the Help, we can find some information about such fields, such as
the following :
Status Indicator (task field)
Data Type Indicator
Entry Type Calculated
Description The Status Indicator field displays an icon which represents
the current status of a task. There are indicators to specify that a task is
Complete, On Schedule, Late, or a Future Task.
How Calculated Microsoft Project bases the content of the Status Indicator
field on the results in the Status field.
If the task is complete, then the Status Indicator contains a check mark.
If the task will occur in the future, the Status Indicator field is blank.
If the task is on schedule, the Status Indicator contains a clock with a
check mark.
If the task is late, the Status Indicator contains a clock with an
exclamation point.
Best Uses Add the Status Indicator field to a task view when you want to
get a quick visual on task status. Use the Status Indicator field in
conjunction with the Status field to be able to group, filter, or sort by
task status.