There is a column in the thick client called "Status Indicator" - viewable in
the Gantt View. Where can I find this on web access? I can't see it in the:
Admin - Manage Views - New View - Types (Project, Portfolio, etc) Its not
visible in any of the types! Why not? My goal is to be able to manage a way
to track late tasks through various ways.
 
D

Dale Howard [MVP]

Ryan --

The field is only visible in Microsoft Project Professional and is not
accessible in PWA. If you need this kind of functionality, you would need
to create a custom enterprise Task field which contains a formula of some
type and which a shows graphical indicators. You would also need to include
this custom field in one or more detailed Project views in PWA. Refer to
the following FAQ for a sample on how to create a custom field containing a
formula and graphical indicators:

http://www.projectserverexperts.com/Shared Documents/CreateStoplightIndicators.htm

Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top