C
CB
Does anyone know what formula project uses to determine the Status of a task?
Thanks in advance.
clvl
Thanks in advance.
clvl
JulieS said:Hello CB,
The actual data in the Status field is numbers with the following
correlation to what you see in the field:
Complete = 0
On Schedule = 1
Late = 2
Future Task = 3
So, you can create the formula in the Text10 field which simply
says:
[Status]
When you click the Graphic Indicators, create your test referencing
each of the numbers in turn. For example:
Equals 0 and then pick whatever graphic you wish for complete
Equals 1 and pick whatever graphic you wish for tasks which are on
schedule
Repeat for Late (2) and Future Tasks (3).
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
CB said:JNB,
Thanks for your reply. I should have been more detailed in what I
am trying
to do. I would like to create in a suctome field (Text 10) a
graphical
indicator based on the status field Status. If Status filed
contains late
for Task 1 then Text 10 shows Red Radio button, if it is on
schedule it shows
a Green radio button.
Any ideas?
Thanks,
clvl
CB said:Julie,
Thanks,
This worked just as I wanted. Is there a way to insert additional
graphical
indicator outside what project has in it's list. For instance if
I found
something on the web or another program, can this be added to that
predefined
list in Project?
CB
JulieS said:Hello CB,
The actual data in the Status field is numbers with the following
correlation to what you see in the field:
Complete = 0
On Schedule = 1
Late = 2
Future Task = 3
So, you can create the formula in the Text10 field which simply
says:
[Status]
When you click the Graphic Indicators, create your test
referencing
each of the numbers in turn. For example:
Equals 0 and then pick whatever graphic you wish for complete
Equals 1 and pick whatever graphic you wish for tasks which are
on
schedule
Repeat for Late (2) and Future Tasks (3).
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
CB said:JNB,
Thanks for your reply. I should have been more detailed in
what I
am trying
to do. I would like to create in a suctome field (Text 10) a
graphical
indicator based on the status field Status. If Status filed
contains late
for Task 1 then Text 10 shows Red Radio button, if it is on
schedule it shows
a Green radio button.
Any ideas?
Thanks,
clvl
:
Hi CB,
Pls check the online help pages:
Status Indicator field at
http://office.microsoft.com/en-us/project/HP430085881033.aspx
In case you need more info on the fields, check list of help
pages on
available fields at
http://office.microsoft.com/en-us/project/HA102369301033.aspx
-JNB
:
Does anyone know what formula project uses to determine the
Status of a task?
Thanks in advance.
clvl
JulieS said:Hello JNB,
Default end time is defined in Tools > Options, Calendar tab. The
default start time is 08:00 the default end time is 17:00. The best
practice is to have those defaults match the project calendar
definition. As noted on the Calendar tab, the default start and end
times are used if you enter an actual start or actual finish date
without entering a time. If however, you record actual values (6
hours of work on a day) the actual end date may be different.
To view the precise times, change the format to show date and time
in Tools > Options, View tab.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.