C
Carlo Folini
Hi,
I specify that resources have to insert "actual work" every day by hour in
PWA.
Sometimes happens that a resource (also me!) forget to insert the actual
work done in a working day (or parto of it).
Is there a way to track those mistakes?
The best solution would be that a notification will be sent when a resource
forgot to insert data for a day and if the problem continues the notification
will be sente to the project manager.
Something similar to the status report notification:
*******************************
Thanks in advace for any help
I specify that resources have to insert "actual work" every day by hour in
PWA.
Sometimes happens that a resource (also me!) forget to insert the actual
work done in a working day (or parto of it).
Is there a way to track those mistakes?
The best solution would be that a notification will be sent when a resource
forgot to insert data for a day and if the problem continues the notification
will be sente to the project manager.
Something similar to the status report notification:
*******************************
Send e-mail in the specified frequency for overdue status reports...
Alert resources when their status reports are day(s) week(s) month(s) overdue.
********************************Then alert resources every every other every week the status reports are submitted.
e-mail me only
e-mail my resources
e-mail me and my resources
Thanks in advace for any help