Status Reports

R

rwarren

Does anyone know of a way to copy a previous status report and use it as a basis for a future week?

Thanks - RW
 
S

Sean

RW:

If you're using the status report feature from PWA, set
the frequency and let Project Server handle the rest.
You can always go back and edit an existing status
report. First select request a status report, then
select the option to edit an existing status report.

Hope this helps!

-------------------
Sean Pales
EPM Solutions Group
Bennett Adelson
www.bennettadelson.com
-----Original Message-----
Does anyone know of a way to copy a previous status
report and use it as a basis for a future week?
 