3
303588
Greetings,
Setting up a status indicator view using stoplights. Can't get it to
work. We only update tasks via PWA % complete, not with hours worked
per day. The logic I have been given is as follows ....
Bottom Task Level
1) If task =100% complete - GREEN.
2) If task <100% and Baseline Finish is > 30 calendar days away -
GREEN.
3) If task <100% but >50% and Baseline Finish within 30 calendar days
- GREEN.
4) If task <50% and Baseline Finish within 30 calendar days - YELLOW.
5) If task <100% and Baseline Finish date has past - RED.
The task level status should roll up to each Summary level task.
Overall Project and Summary Level Tasks
A rollup of the bottom level tasks with the same criteria for color
code.
Any help with the formula would be appreciated.
Thanks,
Sam Baker
FedEx Express Business Systems
Setting up a status indicator view using stoplights. Can't get it to
work. We only update tasks via PWA % complete, not with hours worked
per day. The logic I have been given is as follows ....
Bottom Task Level
1) If task =100% complete - GREEN.
2) If task <100% and Baseline Finish is > 30 calendar days away -
GREEN.
3) If task <100% but >50% and Baseline Finish within 30 calendar days
- GREEN.
4) If task <50% and Baseline Finish within 30 calendar days - YELLOW.
5) If task <100% and Baseline Finish date has past - RED.
The task level status should roll up to each Summary level task.
Overall Project and Summary Level Tasks
A rollup of the bottom level tasks with the same criteria for color
code.
Any help with the formula would be appreciated.
Thanks,
Sam Baker
FedEx Express Business Systems