J
JR
Is there a statusing best practices or guidelines available anywhere?
The following are a couple of questions I have regarding statusing
methods and the effect each method might have on critical path
calculations:
1) Task A is a predecessor to Task B. Task A has completed but Task B
cannot start right away. Which is the better method to offset Task B
to the estimated start date:
a) Set a "Start No Earlier Than" date constraint
b) Increase the lag of Task B
2) What are the effects of each method in Question #1 to the total
slack calculation?
Thanks!
J. Rodrigo
The following are a couple of questions I have regarding statusing
methods and the effect each method might have on critical path
calculations:
1) Task A is a predecessor to Task B. Task A has completed but Task B
cannot start right away. Which is the better method to offset Task B
to the estimated start date:
a) Set a "Start No Earlier Than" date constraint
b) Increase the lag of Task B
2) What are the effects of each method in Question #1 to the total
slack calculation?
Thanks!
J. Rodrigo