StatusingDataAccess.GetDataForTask

P

PS2007Beginner

Hello Folks,

I have been reading throughout the forum looking for a solution to a
problem we have. I have noticed that many of you have had the same
issue but the solution hasn't worked for us.

Exception message: StatusingDataAccess.GetDataForTask could not find
pre-cached data.

In the past this error would include a GUID and we would run the query
that locates the tasks associated with the issue and we would take
care of it.

This error did not include a GUID and our query did not turn up any
corrupted tasks. So I am at a loss as where to look for a solution to
this problem. This error occurs when one of our users goes to the "my
tasks" link. He is the only one who recieves this error and it
happens on any machine he uses. We are using MS Project 2007 and
Project Server 2007. Any help or recommendations would be greatly
appreciated.

Have a great day.

Kevin
 