steps to close a project schedule in project server 2003

C

Chaitanya

Can anybody please let me know the steps to close a project schedule in
project server 2003

Thank you,
Chaitanya
 
D

Dharmesh Patel

Hey,

What do you mean "project schedule", do you mean archive a Project Plan?

Regards,

Dharmesh
 
C

Chaitanya

I mean, A project is completed. Now, i want to close the project
schedule(plan).

If i want to close the project schedule or project plan, what are the steps
to do

the same.

Thank you,
Chaitanya.



Now, my
 
C

Chaitanya

Hi:

A project has been completed. Now, i want to close the project schedule
(plan).

Now, if i want to close the project schedule,

1) What are the steps to close a project schedule?

Thank you,
Chaitanya
 
D

Dharmesh Patel

Ok,

In 2003 there is no formal way to archive a Project. There are two ways
that I would recommend:

1. Save the file out as an MPP and place the file on a Network Share and
then delete the project from Project Server 2003.

2. Create a Custom Field with a multi-value field (Active / Archived / etc)
and set the project status to Archived/Closed, and filiter this out from
views in PWA Project Center....

I know that there are a few custom utilites which can help you with this,
please let m know if you are interested.

Hope this helps.

Dharmesh

(please rate this post if this has helped you)
 
C

Chaitanya

Hi Dharmesh:

Thank you very much for your answer.

Can you please let me know the custom utilites which can help me on this.

Thank you,
Chaitanya.
 
G

GirlGeek

Hi Dharmesh:

Thank you very much for your answer.

 Can you please let me know the  custom utilites which can help me onthis.

Thank you,
Chaitanya.











- Show quoted text -

Hi,

Here's the procedure I institute for project managers:

1 Set the Project State to ‘Completed’:
From the Project menu, select Project Information
Select the value ‘Completed’ in the Project State field
2 Change all resources to type ‘proposed’:
From the Tools menu, select Build Team from Enterprise
On the right side, select ‘Proposed’ instead of ‘Committed’ for the
Booking Type for each resource on the project team
3 Publish your plan:
From the Collaborate menu, select Publish, then All information
4 Send email to <insert Administrator's name here> to move the project
to the Archive folder.
5 Celebrate!
====================/
The 'Project State' field is a custom enterprise text field with gets
set by the project manager as the state changes. The values list I
have is: In Progress, Cancelled, On Hold, Completed

I've created a security category called 'Archived Projects' which deny
open and save permissions to the completed projects to project
managers. As a manager sends me the email that a project is complete,
I move it to the Archived category. This has worked well for us. When
we were audited, and some folks needed access to archived projects, I
just moved them back out of the Archived category and gave them
access.

Let me know if you want any further clarification,

Aviva
 
D

Dale Howard [MVP]