Hi Dharmesh:
Thank you very much for your answer.
Can you please let me know the custom utilites which can help me onthis.
Thank you,
Chaitanya.
- Show quoted text -
Hi,
Here's the procedure I institute for project managers:
1 Set the Project State to ‘Completed’:
From the Project menu, select Project Information
Select the value ‘Completed’ in the Project State field
2 Change all resources to type ‘proposed’:
From the Tools menu, select Build Team from Enterprise
On the right side, select ‘Proposed’ instead of ‘Committed’ for the
Booking Type for each resource on the project team
3 Publish your plan:
From the Collaborate menu, select Publish, then All information
4 Send email to <insert Administrator's name here> to move the project
to the Archive folder.
5 Celebrate!
====================/
The 'Project State' field is a custom enterprise text field with gets
set by the project manager as the state changes. The values list I
have is: In Progress, Cancelled, On Hold, Completed
I've created a security category called 'Archived Projects' which deny
open and save permissions to the completed projects to project
managers. As a manager sends me the email that a project is complete,
I move it to the Archived category. This has worked well for us. When
we were audited, and some folks needed access to archived projects, I
just moved them back out of the Archived category and gave them
access.
Let me know if you want any further clarification,
Aviva