When i log onto from the project server, i get:
Updates
You have 4 task changes from resources pending for approval.
But when i click on that link or go to the updates tab, i get:
Your resources have not submitted any task changes.
To receive information about task changes from your resources, you must
publish assignments to Project Server. To publish assignments, click
Collaborate, point to Publish, and then click New and Changed Assignments.