S
Sundos Masri
hello.
I have inserted the follwoing formula on a project plan: IIf([%
Complete]>=80,"Green",IIf([% Complete]>=50,"Yellow","Red")). if %
complete>= 80 then make it green, if % complete>= 50 then make it yellow and
if not then make it Red.
the above formula is not looking at the start date first?
I would prefer to look at the date first, if the start date is less than the
current date, then look at the percent complete to determine the color. If
the task isn’t scheduled to start yet, then it should be blank (no color).
So how can I correct the formula or what step should I take to do exactly
that. Please advise.
Thanks
SM
I have inserted the follwoing formula on a project plan: IIf([%
Complete]>=80,"Green",IIf([% Complete]>=50,"Yellow","Red")). if %
complete>= 80 then make it green, if % complete>= 50 then make it yellow and
if not then make it Red.
the above formula is not looking at the start date first?
I would prefer to look at the date first, if the start date is less than the
current date, then look at the percent complete to determine the color. If
the task isn’t scheduled to start yet, then it should be blank (no color).
So how can I correct the formula or what step should I take to do exactly
that. Please advise.
Thanks
SM