Stoplight indicators using current date instead of Baseline?

A

anovak

Has anyone developed a comprehensive way to use the current date for
schedule, cost stoplight indicators?

Dale, your article @ ProjectExperts about creating the stoplights is
super. I was just thinking if we are dependent up on the PMs to create
the baseline, what is there to stop them from re-baselining each and
every time they save the plan? Wouldn't it be all green all the time
then?

Please advise.

Thanks,
Andy Novak
University of North Texas
 
G

gobogo90

Andy-

That's indeed a problem. What's worked for us is to allow baselining
for just a few key people and setting up new roles based on the changes
to default rights. All this is done via the Admin functions in PWA.
If you want more detail follow up with me directly and I can walk you
through it.

Greg Steinbach
EPM Solutions Practice
(e-mail address removed)
 