Stoplights: Tasks, Summary Tasks, Project Summary

C

Chicago2Paris

Hi,

I'm using 2003 Pro and have managed to create a simple formula to display
stoplights. However, they only appear in the Tasks rows, not the Summary
Task rows or top-level Project Summary row. Is this possible to do?
 
S

Sean Hanson

When you set up the Task Field, for Calculation for task and group summary
rows, did you select Rollup: Aver, Max, Min, Sum???
--
Sean Hanson

http://www.randsmanagement.com
Mass Resource Tool for 2007
Project Server 2007 Archive Tool
2007 ULS Log Reporting
 
J

Jim Aksel

On the Customize Fields dialog box, in the task and group summary rows you
need to select "Use formula" and the tasks will be treated the same as detail
tasks.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 
C

Chicago2Paris

Thanks, Jim. Both yours and Sean's response above addressed this issue,
depending on how I wanted to handle it.
 