Hi Dale,
Thank you very much for your, as always, invaluable input. I have done as
suggested, and this seems to work AOK for % Work Complete. However, there
is
an issue with the % complete. I have the indicators set as follows (and
copied fomr the enterprise task into the enterprise project code, so they
are
identical):
Is greater than or equal to 75% = Red
Is greater than or equal to 50% = Amber
Is greater than or equal to 25% = Green
Is less than 25% = Smiley Green
And yet quite there are some real oddities, such as:
Task lines go from Smiley green to Green at 4%, to Amber at 5%, and to red
from 14% (lowest % that is red). For summary tasks, however, they remain
smiley green up to 10% (highest %), and I just do not understand.
So, firstly I would like to understand what is going on here, and if you
have any insight I would really appreciate it. I feel like I must be
missing
something really obvious.
Secondly, I think that in fact the most useful thing for our organisation
would be to have a measure of how far the finish date is frmo the baseline
finish. Can you recommend a way of showing a stoplight to indicate eg
10day
after baseline finish = amber, 20day = red etc.
Thanks in advance for your help,
John
Dale Howard said:
John --
Create a new custom enterprise Project number field that contains one of
the
following formulas:
[% Complete]
[% Work Complete]
The first formula calculates the percentage of the Duration "used up" to
date and the second calculates the percentage of the Work actualy
performed
to do. Create your graphical indicator criteria according to your needs.
Hope this helps.
BTOjohn said:
Hi All,
I have followed the excellent instructions on the MSPExperts site to
set
up
the stoplight indicators, both for Work Variance and Finish Variance.
Since
we have a variety of projects, some as little as a dozen days, some
several
thousand, defining a stoplight by number of days is good, but not
perfect.
Is
there a way to set the stoplights based on a percentage of work, or
percentage of duration? eg once 75% of work is done light goes amber,
and
at
90% light goes red?
Thanks in advance,
John