Naomi Nissen
I posted this previously but got no bites. I'm wondering if it's
because this is too much to ask in one post or if it's undoable.
I'd like to accomplish:
1. Create a column in Project Pro that allows a project manager to go
into an individual task and flag it if it's critical to the deadline.
2. Use that flag to create a stoplight for that task only (not the
non-
critical tasks) if it is overdue.
3. Allow the stoplight to go back to another color if the task is
finished, even if it's finished late.
4. Have a stoplight in PWA for any projects that are delayed by these
late tasks.
Thanks
Naomi
because this is too much to ask in one post or if it's undoable.
I'd like to accomplish:
1. Create a column in Project Pro that allows a project manager to go
into an individual task and flag it if it's critical to the deadline.
2. Use that flag to create a stoplight for that task only (not the
non-
critical tasks) if it is overdue.
3. Allow the stoplight to go back to another color if the task is
finished, even if it's finished late.
4. Have a stoplight in PWA for any projects that are delayed by these
late tasks.
Thanks
Naomi