S
Simon Dullingham
I've been discussing in the project group ways of managing infrequent
overhead tasks (like QC, data management, Project Management, etc) One
solution is to set aside a pool of hours for a fixed period (say a month)
and just assign them at the end of the month - i.e. 15 hours on the 30
April. Set the timesheets in PWA to show 4 weeks ahead and allow people to
pre-book against overhead tasks as needed.
(I'm not sure if this makes any sense, but I'm trying not to repeat
everything in another forum).
Anyway, let's say the PM on a project books jsut 5 hours. I then want to
zero his hours at the close of the month, and then stop him from booking
against April's hours in May. i.e. he has to use his pool of 15 hours in
May.
So is there a way of locking out a task so that it cannot be booked against
(like the lock timesheet feature for past time periods), or removing a task
from a timesheet (like the changing a resource to proposed in the Enterpise
Resource dialog)?
Thanks,
Simon
overhead tasks (like QC, data management, Project Management, etc) One
solution is to set aside a pool of hours for a fixed period (say a month)
and just assign them at the end of the month - i.e. 15 hours on the 30
April. Set the timesheets in PWA to show 4 weeks ahead and allow people to
pre-book against overhead tasks as needed.
(I'm not sure if this makes any sense, but I'm trying not to repeat
everything in another forum).
Anyway, let's say the PM on a project books jsut 5 hours. I then want to
zero his hours at the close of the month, and then stop him from booking
against April's hours in May. i.e. he has to use his pool of 15 hours in
May.
So is there a way of locking out a task so that it cannot be booked against
(like the lock timesheet feature for past time periods), or removing a task
from a timesheet (like the changing a resource to proposed in the Enterpise
Resource dialog)?
Thanks,
Simon