I am working on a quite large project, which is to be devided in
several logical parts. For each part there is a seperate project-file
and where necessary there are cross-project-links between tasks of the
different files.
At last all seperate sub-project files have a series of important
milestones to be monitored in the master project file, where all sub-
project files are inserted as linked projects.
In the master project file each sub-project milestone is linked to a
kind of 'commission milestone', all with a Must Start On of Must
Finish On constraint to be referred to.
Now, when opening the master file in Microsoft Project, the planning
wizard dialog box may appear warning for a scheduling conflict on
changed sub-project-milestones linked to the 'mandatory' milestones.
These warnings simply can be ignored, choosing for the option
'Continue, allow scheduling conflict'.
There is also a cross-project-link dialog box. If there are any
differences caused by linked tasks in external projects , this box
will pop up immediately after opening your project file. You will be
able to accept or unlink, and that's just my problem. Of course I
don't want to unlink and so I will have to accept, but after accepting
I cannot see the differences anymore.
Now I am looking for some possiblity of automatically storing the
important (from external linked) tasks just (and only) before every
file save. Baseline Start1/Finish1 would be fine, but it has to be
done automatically.
Any suggestions?
Regards, Luc
several logical parts. For each part there is a seperate project-file
and where necessary there are cross-project-links between tasks of the
different files.
At last all seperate sub-project files have a series of important
milestones to be monitored in the master project file, where all sub-
project files are inserted as linked projects.
In the master project file each sub-project milestone is linked to a
kind of 'commission milestone', all with a Must Start On of Must
Finish On constraint to be referred to.
Now, when opening the master file in Microsoft Project, the planning
wizard dialog box may appear warning for a scheduling conflict on
changed sub-project-milestones linked to the 'mandatory' milestones.
These warnings simply can be ignored, choosing for the option
'Continue, allow scheduling conflict'.
There is also a cross-project-link dialog box. If there are any
differences caused by linked tasks in external projects , this box
will pop up immediately after opening your project file. You will be
able to accept or unlink, and that's just my problem. Of course I
don't want to unlink and so I will have to accept, but after accepting
I cannot see the differences anymore.
Now I am looking for some possiblity of automatically storing the
important (from external linked) tasks just (and only) before every
file save. Baseline Start1/Finish1 would be fine, but it has to be
done automatically.
Any suggestions?
Regards, Luc