G
Gil
Hi,
We are using Project Server 2007 (SP1 + Infrastructure update
installed):
The Project manager noticed that in some tasks which he is assigned
to, there are "strange" actual work values IN THE FUTURE (4.98h, 1.03h
etc.), which were NOT reported by him.
Progress is reported regularly through PWA.
Tasks were created as (and still are) Fix Unit type, and usually are
planned to 100-300 hours.
Does anyone have an idea why it happens and how to solve/avoid this
issue?
Thanks, Gil.
We are using Project Server 2007 (SP1 + Infrastructure update
installed):
The Project manager noticed that in some tasks which he is assigned
to, there are "strange" actual work values IN THE FUTURE (4.98h, 1.03h
etc.), which were NOT reported by him.
Progress is reported regularly through PWA.
Tasks were created as (and still are) Fix Unit type, and usually are
planned to 100-300 hours.
Does anyone have an idea why it happens and how to solve/avoid this
issue?
Thanks, Gil.