Strange behaviour in timesheet functionality

F

Flemming Goldbach

We are currently user testing Project Server 2007 timesheet functionality.
We have come across a couple of situations where a user enters time on a
given administrative task, presses save, and after the screen has refreshed
the time entered on that given task has disappeared and have not been saved.

The problem is after this easily reproducable for that users timehseet. We
have even tried to enter 1 hours into every admniistrative task line on a
given day, and after pressing save all of the 1s are saved except for the
task that originally had the problem!

The same happens if we submit the timesheet, and try to use Adjust
timesheet, and only for that one task line.

There are no differences in "Always Display", "Non-working/Working"
parameters of the administrative tasks, and none of them require approval.

Any ideas, please?
 