Strange changes in Actual Work make change in Work

A

Andrea

Background:
- SP1 + hotfix Server side
- SP2 client side
- Timesheet View
Scenario:
- There's a task with 10 h of Work (scheduled). A resource updates Actual
Work as 20h. Automatically the view updates the Work to 20h. If the resource
changes (before sending to PM for approval and, anyway with NO SAVE ) again
the Actual Work , for example to 12h, the system DOESN'T UPDATE THE WORK to
12h!!!!!
So, changes in Actual Work make change in Work, isn't true everytime. If the
Actual Work is higher than Work, there is no way to come back to the old
value of work.
Bye
 
M

Mike Glen

Hi Andrea,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top