Background:
- SP1 + hotfix Server side
- SP2 client side
- Timesheet View
Scenario:
- There's a task with 10 h of Work (scheduled). A resource updates Actual
Work as 20h. Automatically the view updates the Work to 20h. If the resource
changes (before sending to PM for approval and, anyway with NO SAVE ) again
the Actual Work , for example to 12h, the system DOESN'T UPDATE THE WORK to
12h!!!!!
So, changes in Actual Work make change in Work, isn't true everytime. If the
Actual Work is higher than Work, there is no way to come back to the old
value of work.
Bye
- SP1 + hotfix Server side
- SP2 client side
- Timesheet View
Scenario:
- There's a task with 10 h of Work (scheduled). A resource updates Actual
Work as 20h. Automatically the view updates the Work to 20h. If the resource
changes (before sending to PM for approval and, anyway with NO SAVE ) again
the Actual Work , for example to 12h, the system DOESN'T UPDATE THE WORK to
12h!!!!!
So, changes in Actual Work make change in Work, isn't true everytime. If the
Actual Work is higher than Work, there is no way to come back to the old
value of work.